IIBA IIBA exam demos contain reliable along with valuable questions & answers that will offer an individual abundant main points to pass your exam on your initial try. They cover every one of the topics in the IIBA exam. Passing your exam will be a breeze for you. One of the obvious along with distinct features of our IIBA CBAP exam dumps is that this guarantees the success in the real assessment room. Get certified along with full confidence along with hunt for a very good job. We all also present you with the complete refund policy. If you don?¡¥t pass your IIBA IIBA CBAP certification exam after employing our exam demos at the first attempt, you simply need to email us your failed transcript, and you will get the income back before long.

2021 Oct CBAP sample question

Q201. - (Topic 2) 

What element of the conduct elicitation activity is tracked to provide a basis for future planning? 

A. Time actually spent eliciting the requirements 

B. Number of stakeholders that did not participate in the requirements elicitation 

C. Cost of actually eliciting the requirements 

D. Changes that entered the scope throughout the requirements elicitation activities 

Answer: A 


Q202. - (Topic 1) 

You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex. What thing adds to the level of complexity among requirements? 

A. Relationships among the requirements 

B. Management in the project 

C. Stakeholders in the project 

D. Cost and schedule constraints 

Answer: A 


Q203. - (Topic 3) 

There are 50 stakeholders in the current project. How many communication channels exist in this project? 

A. 1200 

B. 1225 

C. 1500 

D. 500 

Answer: B 


Q204. - (Topic 1) 

You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?

A. A change management system

B. A repository

C. A project scope statement

D. A requirements register

Answer: B


Q205. - (Topic 3) 

The business process model is also known as _________. 

A. Organization model 

B. Activity model 

C. Relational model 

D. Data flow model 

Answer: B 


CBAP exam guide

Latest CBAP exam topics:

Q206. - (Topic 3) 

You are completing the prepare for elicitation process for an identified problem in your organization. The prepare for elicitation process requires three inputs for this process. Which one of the following is not an input that will help you prepare for the elicitation activities? 

A. Stakeholder list 

B. Stakeholder concerns 

C. Business need 

D. Solution scope 

Answer: B 


Q207. - (Topic 1) 

Your organization is using a plan-driven approach to business analysis. What characteristic must be true of changes in the approach that your organization is using? 

A. All the changes only occur if they are less than an agreed factor, such as ten percent of the solution's overall cost or a percentage of the project's schedule. 

B. All the changes only occur if they are less than ten percent of the solution's overall cost. 

C. All the changes only occur if they are genuinely necessary. 

D. Changes are generally not permitted in the plan-driven approach to business analysis. 

Answer: C 


Q208. - (Topic 1) 

Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A. What is the opportunity cost in this scenario? 

A. $331013 

B. There is not enough information to know as the risk for Project B has not been quantified. 

C. $235,987 

D. $567,000 

Answer: C 


Q209. - (Topic 3) 

Which of the following is a method of displaying the timelines of all the various subtasks that are involved in any project? 

A. Pie chart 

B. Scatter chart 

C. Activity network diagram 

D. Cost-benefit analysis 

Answer: C 


Q210. - (Topic 1) 

You are the business analyst for the NGQ Company. Management is concerned that their company is not able to meet an identified business need with their current existing structure, people, processes and technology. They've asked you to complete an analysis of their organization's ability to meet the identified business need. What business analysis process are you completing for your organization? 

A. Determining the solution approach 

B. Assessing the capability gaps 

C. Requirements elicitation 

D. Verifying the requirements 

Answer: B