Proper study guides for Up to date IASSC IASSC Certified Lean Six Sigma Green Belt certified begins with IASSC ICGB preparation products which designed to deliver the Breathing ICGB questions by making you pass the ICGB test at your first time. Try the free ICGB demo right now.
Q16. To create standardization of financial benefit calculations project savings are typically based on savings over what period of time?
A. 6 months
B. 12 months
C. 24 months
D. The remainder of the calendar year
E. The remainder of the fiscal year
Answer: B
Q17. Which of these is Discrete data?
A. Train arrived at 4:17 pm.
B. Race car consumed 23 gallons of fuel.
C. Of the 42 people on the bus, 12 went into the station.
D. It took 3 hours and 32 minutes to complete the marathon.
Answer: C
Q18. In the late 1980’s William Smith coined the name Six Sigma for a methodology that had its origins at __________________ for quality related work being done there.
A. Honeywell
B. Allied Signal
C. General Electric
D. Motorola
Answer: D
Q19. A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data: Cutting38 Forming17 Stitching56 Sealing42
A. Forming, Sealing, Cutting, Stitching
B. Sealing, Stitching, Forming, Cutting
C. Stitching, Sealing, Cutting, Forming
D. Forming, Cutting, Sealing, Stitching
Answer: C
Q20. Which element of waste best describes the cost of a resource being in the queue?
A. Waiting
B. Motion
C. Inventory
D. Correction
Answer: A
Q21. The practice of utilizing Poka-Yoke is also known as ________________.
A. Thorough integration
B. Mistake proofing
C. On site inspection
D. Lean controls
Answer: B
Q22. The Standard Deviation for the distribution of Means is called the ___________ and approaches zero as the sample size reaches 30.
A. Standard Error
B. Mean Deviation
C. Mean Spread
D. Mean Error
Answer: A
Q23. The use of station warning lights, tool boards and jidohka devices in the application of Lean accomplish which of these principles?
A. Pilferage Minimization
B. Visual Factory
C. Management Awareness
D. Operator Attentiveness
Answer: B
Q24. Measurement System Analysis is a procedure used to quantify all ____________ in the method or system used for taking measurements.
A. Totals
B. People involved
C. Variation
D. Summations
Answer: C
Q25. A process can be defined as a repetitive and systematic series of steps or activities where inputs are modified or assembled to achieve a _______________ result.
A. Revenue total
B. Month end
C. Customer desired
D. Budgeted
Answer: C
Q26. Customers make a purchase decision based on a number of factors. In Lean Six Sigma we refer to these decision points as CTQ’s which stands for __________.
A. Cost of the quantity
B. Conscious thought qualities
C. Conspicuous time quandaries
D. Critical-to-quality
Answer: D
Q27. The Central Limit Theorem helps us understand the ___________ we are taking and is the basis for using sampling to estimate population parameters.
A. Analysis
B. Kurtosis
C. Risk
D. Route
Answer: C
Q28. Customers make a purchase decision based on a number of factors. In Lean Six Sigma we refer to these decision points as CTQ’s or as ____________________.
A. Critical-to-quality
B. Conscious thought qualities
C. Conspicuous time quandaries
D. Cost of the quantity
Answer: A
Q29. What is the Cycle Time, in seconds, for a process having a Throughput of 7,200 units per hour?
A. 0.5
B. 2
C. 4
D. 10
Answer: A
Q30. Bias in Sampling is an error due to lack of independence among random samples or due to systematic sampling procedures.
A. True
B. False
Answer: A