Our pass rate is high to 98.9% and the similarity percentage between our PMI-001 study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI PMI-001 exam in just one try? I am currently studying for the PMI PMI-001 exam. Latest PMI PMI-001 Test exam practice questions and answers, Try PMI PMI-001 Brain Dumps First.

Online PMI-001 free questions and answers of New Version:

NEW QUESTION 1
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

  • A. Define Activities
  • B. Direct and Manage Project Work
  • C. Develop Project Management Plan
  • D. Develop Project Charter

Answer: D

NEW QUESTION 2
A risk that arises as a direct result of implementing a risk response is called a:

  • A. contingent risk
  • B. residual risk
  • C. potential risk
  • D. secondary risk

Answer: D

NEW QUESTION 3
What type of reward can hurt team cohesiveness?

  • A. Sole-sum
  • B. Win-lose
  • C. Lose-win
  • D. Partial-sum

Answer: B

NEW QUESTION 4
What is a hierarchically organized depiction of the identified project risks arranged by risk category?

  • A. Risk register
  • B. Risk breakdown structure (RBS)
  • C. Risk management plan
  • D. Risk category

Answer: B

NEW QUESTION 5
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  • A. Collect Requirements
  • B. Plan Scope Management
  • C. Define Scope
  • D. Define Activities

Answer: A

NEW QUESTION 6
At which stage of team development do members begin to work together, adjust work
habits, and trust each other?

  • A. Forming
  • B. Storming
  • C. Norming
  • D. Performing

Answer: C

NEW QUESTION 7
The following is a network diagram for a project.
The total float for the project is how many days?

  • A. 3
  • B. 5
  • C. 7
  • D. 9

Answer: A

NEW QUESTION 8
A procurement management plan is a subsidiary of which other type of plan?

  • A. Resource plan
  • B. Project management plan
  • C. Cost control plan
  • D. Expected monetary value plan

Answer: B

NEW QUESTION 9
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern?

  • A. There is a cost under ru
  • B. There is a cost overru
  • C. May not meet deadlin
  • D. The project is 20 days behind schedul

Answer: B

NEW QUESTION 10
Which of the following factors is lowest at the start of the project?

  • A. Cost of changes
  • B. Stakeholder influences
  • C. Risk
  • D. Uncertainty

Answer: A

NEW QUESTION 11
Which items are components of a project management plan?

  • A. Change management plan, process improvement plan, and scope management plan
  • B. Agreements, procurement management plan, and work performance information
  • C. Schedule management plan, project schedule, and resource calendars
  • D. Scope baseline, project statement of work, and requirements traceability matrix

Answer: A

NEW QUESTION 12
Which of the following is an example of schedule compression?

  • A. Activity sequencing
  • B. Resource leveling
  • C. Lead and lag adjusting
  • D. Crashing

Answer: D

NEW QUESTION 13
An input to the Plan Procurement Management process is:

  • A. Source selection criteri
  • B. Market researc
  • C. Astakeholder registe
  • D. Arecords management syste

Answer: C

NEW QUESTION 14
Who is responsible for reviewing change requests and approving or rejecting the change requests?

  • A. Change control board
  • B. Project manager
  • C. Project management office
  • D. Project sponsor

Answer: A

NEW QUESTION 15
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

  • A. Determine Budge
  • B. Baseline Budge
  • C. Control Cost
  • D. Estimate Cost

Answer: A

NEW QUESTION 16
......

Recommend!! Get the Full PMI-001 dumps in VCE and PDF From Downloadfreepdf.net, Welcome to Download: https://www.downloadfreepdf.net/PMI-001-pdf-download.html (New 918 Q&As Version)