Want to know Pass4sure PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Simulation CompTIA PK0-003 answers to Replace PK0-003 questions at Pass4sure. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2021 Apr PK0-003 exam cost

Q11. - (Topic 2) 

Which of the following are objectives of the project kick-off meeting and common activities 

performed during this meeting? (Select FOUR). 

A. Describe the work breakdown structure 

B. Present the roles and responsibilities 

C. Describe the project goals and objectives 

D. Present a high level project timeline 

E. Communicate stakeholder expectations 

F. Present the management plan 

G. Present the communication plan 

H. Communicate the detailed budget 

Answer: B,C,D,E 


Q12. - (Topic 1) 

Which of the following components of the project charter is used to help determine the project’s communication needs? 

A. Stakeholder identification 

B. Project objectives 

C. Problem statement 

D. Key deliverables 

Answer:


Q13. - (Topic 3) 

Which of the following are included in a risk register? (Select TWO). 

A. Project risk responses 

B. Identified risks 

C. Major milestones 

D. Risk analysis tools 

E. Risk control board members 

Answer: A,B 


Q14. - (Topic 2) 

A key stakeholder calls the project manager and asks to include an enhancement to the product which should be simple to implement. If the project manager agrees to this enhancement, which of the following components of the project plan will be MOST impacted? 

A. Scope 

B. Risk 

C. Quality 

D. Resource 

Answer:


Q15. - (Topic 2) 

Which of the following are valid conflict resolution techniques? 

A. Smoothing, forcing, compromising, avoiding, and influencing 

B. Smoothing, forcing, considering, avoiding, and negotiating 

C. Smoothing, enforcing, compromising, avoiding, and negotiating 

D. Smoothing, forcing, compromising, avoiding, and negotiating 

Answer:


Updated PK0-003 real exam:

Q16. - (Topic 2) 

Which of the following conflict management techniques is represented by making concessions to maintain team harmony? 

A. Smoothing 

B. Negotiating 

C. Collaborating 

D. Avoiding 

Answer:


Q17. - (Topic 2) 

Which of the following techniques provides the MOST positive outcomes to conflict? (Select THREE). 

A. Forcing 

B. Smoothing 

C. Influencing 

D. Negotiating 

E. Avoiding 

F. Convincing 

G. Socializing 

H. Compromising 

I. Confronting 

Answer: B,D,H 


Q18. - (Topic 2) 

A task leader for a project states that to complete the task on time, more money and three more people will be required. Which of the following change management procedures is being performed? 

A. Identified options 

B. Risk analysis 

C. Identified change 

D. Impact analysis 

Answer:


Q19. - (Topic 2) 

In a project manager’s status report, it shows an earned value of $40,000 and actual costs of $39,000 with a planned value of $55,000. Which of the following is the Cost Performance Index (CPI) of this project and is it ahead or behind schedule? 

A. CPI = 1.38, ahead of schedule 

B. CPI = 0.72, behind schedule 

C. CPI = 1.03, behind schedule 

D. CPI = 0.98, ahead of schedule 

Answer:


Q20. - (Topic 3) 

While working on a project, senior management has requested a special report be created and distributed. This was not previously included in the communication management plan. Which of the following should the project manager do FIRST? 

A. Immediately incorporate the request into the plan. 

B. Delegate the creation of the report to a team member. 

C. Add the request to the project manager’s responsibilities. 

D. Generate a change request to be submitted. 

Answer: