Q131. - (Topic 3) 

During which of the following process groups is the project charter developed? 

A. Pre-project setup 

B. Project execution 

C. Project planning 

D. Project control 

Answer: A 


Q132. - (Topic 3) 

A project manager has been working on a project for several months and the final deliverable has just been accepted by the customer. The project team is already preparing for transition to future projects, and the project manager drafts a memo reminding the project team that there are a few more tasks to complete before the team is released. The project manager is MOST likely to address which of the following tasks in the memo? (Select TWO). 

A. Validating the project charter 

B. Recognizing the project sponsor 

C. Hosting a lessons-learned event 

D. Developing the risk register 

E. Developing final cost reports 

Answer: C,E 


Q133. - (Topic 1) 

Which of the following shows how often contracts would be closed for the procurements on a project? 

A. During phase gate review 

B. After the project is completed 

C. At the end of the project 

D. At the end of the contract 

Answer: D 


Q134. - (Topic 2) 

A project activity has a schedule that allows a late start on day 10 and a late finish on day 

20. The project manager has determined an early start could occur on day 7 with an early finish on day 14. Which of the following does this schedule identify? 

A. A lead 

B. A buffer 

C. A float 

D. A lag 

Answer: C 


Q135. - (Topic 3) 

A project manager is finding that weekly team meetings are not well attended and those who do attend do not always contribute to the discussion. Which of the following identifies the BEST approach for the project manager to address these issues? 

A. Change meetings to every other week to accommodate busy schedules 

B. Meet individually with each team member to discuss their attendance and participation 

C. Develop a clearly defined agenda with opportunities for all to participate 

D. Invite additional stakeholders to participate in the weekly team meetings 

Answer: C 


PK0-003 sample question

Renew PK0-003 training:

Q136. - (Topic 1) 

An active project has an EV of 50,000, an AC of 45,000, and a PV of 50,000. Which of the following represents the current project CPI? 

A. .9 

B. 1 

C. 1.1 

D. 5000 

Answer: C 


Q137. - (Topic 3) 

Construction on a new building has been delayed by two weeks due to rain. With no additional resources or budget available, the project manager must implement some type of resource leveling in hopes of completing the project on time. Which of the following is the project manager MOST likely to do? 

A. Complete tasks originally scheduled in sequence to be done in parallel 

B. Reduce the scope of the planned deliverable 

C. Increase the number of staff working on the remaining tasks 

D. Increase the daily work hours of the personnel working on the project 

Answer: A 


Q138. - (Topic 2) 

A project manager is preparing to start another project that is identical to one that was just completed. Which of the following is the BEST way to estimate the cost of the new project? 

A. Parametric estimation 

B. Bottom-up estimation 

C. Resource cost estimation 

D. Analogous estimation 

Answer: D 


Q139. - (Topic 2) 

A task leader for a project states that to complete the task on time, more money and three more people will be required. Which of the following change management procedures is being performed? 

A. Identified options 

B. Risk analysis 

C. Identified change 

D. Impact analysis 

Answer: D 


Q140. - (Topic 1) 

Which of the following project plan components would include information regarding the management of issues? 

A. Project Management Plan 

B. Human Resources Plan 

C. Test Mangement Plan 

D. Scope Management Plan 

Answer: A