Want to know Actualtests PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Virtual CompTIA PK0-003 answers to Far out PK0-003 questions at Actualtests. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2021 Oct PK0-003 practice

Q51. - (Topic 1) 

A coworker approaches the project manager regarding a project team member’s prior work ethic. Which of the following is the BEST approach for the project manager to address the information presented? 

A. Do not act on the information presented 

B. Ask the resource manager for another resource 

C. Discuss the issue with human resources 

D. Confront the resource manager about the risk 

Answer: A 


Q52. - (Topic 1) 

A change request has been authorized to decrease the amount of time the project team has to hand over the deliverable to the customer. The project manager has decided to crash the schedule to accommodate the change. Which of the following will MOST likely occur? 

A. The risk of the project will decrease. 

B. The quality of the deliverable will increase. 

C. The cost of the project will increase. 

D. The scope of the project will decrease. 

Answer: C 


Q53. - (Topic 2) 

Which of the following is the BEST indicator of project performance? 

A. Earned value management 

B. Critical chain method 

C. Critical path method 

D. Return on investment 

Answer: A 


Q54. - (Topic 2) 

Which of the following conflict management techniques is represented by making concessions to maintain team harmony? 

A. Smoothing 

B. Negotiating 

C. Collaborating 

D. Avoiding 

Answer: A 


Q55. - (Topic 3) 

Which of the following project management tools helps identify trends? 

A. Network diagram 

B. Run chart 

C. Histogram 

D. Check sheet 

Answer: B 


Updated PK0-003 vce:

Q56. - (Topic 3) 

A project manager receives word from a team member that a modification is required to the product being developed. Which of the following documents should the project manager initially use to document the request? 

A. Risk register 

B. Scope statement 

C. Issue log 

D. Change log 

Answer: D 


Q57. - (Topic 3) 

Which of the following organizational structures is characterized by a group of dedicated project team members? 

A. Strong matrix 

B. Matrix 

C. Functional 

D. Projectized 

Answer: D 


Q58. - (Topic 1) 

Which of the following is a component of a performance evaluation for an individual? 

A. Resource utilization 

B. Role assessment 

C. Scope management 

D. Variance management 

Answer: B 


Q59. - (Topic 3) 

A project manager has been notified that the stakeholders are leaving the company and will no longer be members of the project team. Which of the following components in the project plan will require modification? 

A. Budget 

B. Scope statement 

C. WBS 

D. Risk register 

Answer: D 


Q60. - (Topic 3) 

A project manager is leading a discovery session involving a quality problem discovered in the manufacturing process for a time-sensitive product. In an effort to expedite the process of resolving quality control issues the team would like to focus on improvements that would result in the greatest positive impact to the quality of the product. A data set has been collected over time and is ready for use by the project team. Which of the following graphical data tools would be MOST appropriate to help the project team achieve its stated goals? 

A. Pareto chart 

B. Delphi model 

C. Run chart 

D. Histogram 

E. Ishikawa diagram 