Q181. - (Topic 2) 

Which of the following includes validating the project charter and introducing key members of the team? 

A. Kick-off meeting 

B. Stakeholder register 

C. Team-building event 

D. Communications plan 

Answer:


Q182. - (Topic 1) 

Which of the following risk responses would be characterized by having knowledge of a risk event and taking advantage of the risk? 

A. Accepting 

B. Enhancing 

C. Exploiting 

D. Sharing 

Answer:


Q183. - (Topic 1) 

Which of the following is required to validate a project? 

A. Problem statement 

B. Signed project charter 

C. Key project deliverables 

D. Alignment with the organization’s strategic goals 

Answer:


Q184. - (Topic 3) 

If a project team receives information that the required hardware needed for the project is two weeks behind estimated arrival, which of the following items in the project plan will MOST likely be affected? (Select TWO). 

A. Quality metrics 

B. Project scope 

C. Work breakdown structure 

D. Schedule 

E. Resource requirements 

Answer: D,E 


Q185. - (Topic 2) 

A project timeline is at risk of not meeting the completion time for developing a smart phone application. In order to meet the date, the code can be pushed out to the testers while getting scanned by the code security software. Development time will be shorter, but there could be a security risk to the application. Which of the following techniques does this describe? 

A. Crashing 

B. Avoidance 

C. Optimizing 

D. Fast-tracking 

Answer:


Rebirth PK0-003 free exam questions:

Q186. - (Topic 2) 

A project manager is concerned that the project schedule will extend beyond initial estimation. Which of the following methods will allow the project manager to determine the project duration with the MOST precision? 

A. Gantt 

B. CCM 

C. CPM 

D. PERT 

Answer:


Q187. - (Topic 1) 

A third party product warranty is an example of which of the following types of risk response? 

A. Risk sharing 

B. Risk avoidance 

C. Risk acceptance 

D. Risk transfer 

Answer:


Q188. - (Topic 3) 

A project manager is asked to provide regular status updates to executive management regarding the current project. To effectively manage the distribution of these updates, which of the following should the project manager MOST likely refer to? 

A. Lessons learned library 

B. Stakeholder register 

C. Issue log 

D. Meeting agendas 

Answer:


Q189. - (Topic 2) 

Which of the following describes a WBS? 

A. A schedule-oriented decomposition of the project work 

B. A deliverable-oriented decomposition of the project work 

C. An action-oriented decomposition of the project work 

D. An owner-oriented decomposition of the project work 

Answer:


Q190. - (Topic 3) 

A project manager receives notice that a new law will soon go into effect that may impact a current project. After confirming the information, which of the following should the project manager update FIRST? 

A. Stakeholder register 

B. Risk register 

C. Issue log 

D. Qualitative data 

Answer: