Q71. - (Topic 2) 

A project manager is meeting with the key stakeholders to understand the problem, gather business requirements, and identify project objectives. Which of the following allows this information to be formally documented and allows the project manager to measure success? 

A. Project management plan 

B. Project charter 

C. Request for proposal 

D. Statement of work 

Answer: B 


Q72. - (Topic 3) 

Once user acceptance testing has been completed and approved, the project manager should: 

A. obtain sign-off from the project sponsor. 

B. determine the estimation technique they want to use. 

C. identify the risk management plan. 

D. update the WBS with development estimates. 

Answer: A 


Q73. - (Topic 3) 

The project development team has tested the software code, utilized an automated regression testing tool, and turned the code over to the customer for user acceptance testing. At each level of testing, defects are identified and corrected. This process is an example of: 

A. quality control. 

B. change management. 

C. quality assurance. 

D. change control. 

Answer: A 


Q74. - (Topic 1) 

Which of the following would be found in a post-mortem analysis? (Select TWO). 

A. Lessons Learned 

B. Transition Plan 

C. Project sponsor signoff 

D. Maintenance responsibilities 

E. Reasons for early termination of the project 

Answer: A,E 


Q75. - (Topic 2) 

A project manager has projected an overwhelming response to a product launch. Which of the following BEST describes this event? 

A. A constraint 

B. A risk 

C. A performance index 

D. An issue 

Answer: B 


PK0-003 test

Leading PK0-003 real exam:

Q76. - (Topic 2) 

While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case. Which of the following types of schedule methods will reflect this? 

A. PERT 

B. CPM 

C. CCM 

D. GERT 

Answer: A 


Q77. - (Topic 1) 

Which of the following is the purpose of a post mortem analysis? 

A. Determines the degree of accuracy of activity duration estimates 

B. Compares the initial project baselines to end of project baselines 

C. Highlights detected quality issues and the resolution to the issues 

D. Documents the reasons for an early project closure 

Answer: D 


Q78. - (Topic 1) 

When a project manager is leading the team through the norming stage of team growth, the project team: 

A. is performing in a highly efficient manner. 

B. has reached full capacity. 

C. is seeing a decrease in productivity. 

D. is working together and comfortable. 

Answer: D 


Q79. - (Topic 2) 

A project sponsor has requested significant, additional features to software being developed. Before submitting a change request that will result in changes to the project scope, which of the following activities should the project manager perform? 

A. Impact analysis 

B. Budget analysis 

C. Risk analysis 

D. Make/buy analysis 

E. SWOT analysis 

Answer: A 


Q80. - (Topic 1) 

The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies? 

A. Transferring 

B. Enhancing 

C. Sharing 

D. Exploiting 

Answer: C