The particular PMI PMI-ACP questions are usually up to date by our engineers live. Youre going to get the latest simulated examination questions that are in keeping with the present PMI examination. A lot more importantly, the actual revise day prolonged in order to A hundred and eighty times, displaying that you may have fifty percent a years time and energy to study PMI-ACP dumps.

2021 Sep PMI-ACP free exam questions

Q71. Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat: 

A. Work was removed from the Product Backlog. 

B. Work was added to the Product Backlog. 

C. The team's velocity increased. 

D. The team's velocity decreased. 

Answer: B 


Q72. In Agile risk management, a risk burndown chart is best used to: A. Qualitatively analyze the probability of a risk occurring. 

B. Track progress on risk reduction of technical risks. 

C. Document the external risks that could impact the project. 

D. Illustrate the project risk profile and new and changing risks. 

Answer: D 


Q73. In eXtreme Programming (XP), analysis, design, coding, and testing phases are done: 

A. At the beginning of the iteration. 

B. Every day. 

C. In sequence. 

D. Without documentation. 

Answer: B 


Q74. In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit? 

A. Release planning 

B. Sprint planning 

C. Sprint Retrospective 

D. Daily Scrum 

Answer: C 


Q75. A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called: 

A. Story 

B. Timebox 

C. Iteration 

D. Burndown 

Answer: C 


PMI-ACP latest exam

Rebirth PMI-ACP sample question:

Q76. What are the primary outputs of a release planning session? 

A. Release vision, assumptions, action items, and iteration goals 

B. Prioritized Product Backlog, risks, action items, and release goals 

C. Estimated iteration velocities, risks, action items, and Release Backlog 

D. Risks, action items, dependencies, and Release Backlog 

Answer: D 


Q77. A high-performance Agile team: A. is fully committed to team success yet respects the prescribed roles and titles of team members. 

B. owns its decisions and commitments and is motivated to succeed at any cost. 

C. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement. 

D. produces a high volume of business value through intensive collaboration and avoidance of conflict. 

Answer: C 


Q78. The term .°last responsible moment.± refers to the moment at which: 

A. the iteration testing deadline arrives and code testing must stop. 

B. failing to make a decision eliminates an important alternative. 

C. release planning is complete and the first iteration planning starts. 

D. the implementation date is set and sponsor approval has been received. 

Answer: B 


Q79. Team velocity is used to: 

A. Measure the percentage of features completed. 

B. Judge productivity within the iteration. 

C. Predict schedules for mature teams. 

D. Give feedback on delivered value. 

Answer: C 


Q80. When developing user stories, user expectations are best captured in what form? 

A. Acceptance tests 

B. Entrance criteria 

C. Done criteria 

D. Go and no-go limits 

Answer: A