Master the PMP Project Management Professional content and be ready for exam day success quickly with this Ucertify PMP free practice exam. We guarantee it!We make it a reality and give you real PMP questions in our PMP PMP braindumps.Latest 100% VALID PMP PMP Exam Questions Dumps at below page. You can use our PMP PMP braindumps and pass your exam.
Q286. Which of the following is not a cost of non-conformance?
A. maintenance and calibration
B. warranty repairs
C. All of the other alternatives apply.
D. scrap
E. rework
Answer: A
Q287. The person in the organization that authorizes the commencement of a project is the ______________?
A. Project Admin
B. Sponsor
C. Project Manager
D. Senior Manager
Answer: B
Q288. You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process group. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and who will prepare it is which of the following?
A. Scope management plan
B. Project charter
C. Communications management plan
D. Information distribution plan
Answer: C
Q289. Your project sponsor has requested a cost estimate for the project on which you're working. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide to use ___________________.
A. parametric modeling techniques
B. analogous estimating techniques
C. bottom-up estimating techniques
D. computerized modeling techniques
Answer: B
Q290. What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
A. Organizational Breakdown Structure (OBS)
B. Work Performance Information
C. Work Package
D. Work Breakdown Structure (WBS)
Answer: D
Q291. Which may be employed to shorten a schedule without changing the scope of the task?
A. Alter to task priorities.
B. Releasing resources earlier from tasks which were scheduled with a late start.
C. Fast tracking or Crashing
D. Fast tracking.
E. Crashing
Answer: D
Q292. EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
A. EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]
B. EAC = BAC - AC
C. EAC = 1 - CPI
D. EAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]
Answer: A
Q293. During the opening rounds of contract negotiation, the other party uses a fait accompli tactic. Which of the following statements is true about fait accompli tactics?
A. One party claims the issue under discussion was documented and accepted as part of Scope Verification.
B. One party claims the issue under discussion has already been decided and can't be changed.
C. One party claims to accept the offer of the other party, provided a contract change request is submitted describing the offer in detail.
D. One party agrees to accept the offer of the other party but secretly knows they will bring the issue back up at a later time.
Answer: B
Q294. Which of the following is NOT included in a schedule change control system?
A. Approval levels necessary for authorizing changes
B. Tracking systems
C. Paperwork necessary for making changes
D. Limitations on the scope of changes
Answer: D
Q295. A project involves arranging for the closing of the company office where the team works and relocating everyone to a new city. The BEST thing the project manager can do is:
A. Spend time carefully creating the work breakdown structure.
B. Have a strong quality control plan.
C. Decrease the fringe benefits.
D. Carefully consider the reward system for the project.
Answer: D
Q296. What scope definition technique is used to generate different approaches to execute and perform the work of the project?
A. Build vs. buy
B. Expert judgment
C. Alternatives identification
D. Product analysis
Answer: C
Q297. Risk event probability is defined as:
A. the total number of possible events divided into the expectations or frequency of the risk event
B. the fraction of the total project tasks which may be affected by the risk event
C. the number of times the risk event may occur
D. Both 1) the total number of possible events divided into the expectations or frequency of the risk event and 2) the number of times the risk event may occur.
E. the total number of possible events divided into the consequences of the risk event.
Answer: A
Q298. What tool and technique includes all costs incurred over the life of a product by investment in preventing nonconformance to requirements?
A. Cost of quality
B. Measure of design
C. Statistical control
D. Systematic analysis
Answer: A
Q299. Which of the following is involved in the initiation process group?
A. Develop Project Management Plan
B. Identify Stakeholders
C. Plan Communications
D. Collect Requirements
Answer: B
Q300. Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.
Answer: A