Our pass rate is high to 98.9% and the similarity percentage between our PMP study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMP PMP exam in just one try? I am currently studying for the PMP PMP exam. Latest PMP PMP Test exam practice questions and answers, Try PMP PMP Brain Dumps First.
Q271. You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?
A. Probability of achieving time and cost estimates
B. Watch list of low-priority risks
C. Priority list of risks
D. Risks grouped by categories
Answer: A
Q272. The work that must be done in order to deliver a product with the specified features and functions is:
A. Project verification
B. Project scope
C. Project control
D. Product scope
Answer: B
Q273. During what process is the quality policy determined?
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer: C
Q274. Risk Event Status is defined as _____ .
A. Both 1) the severity of the consequences, and 2)how likely the event is to occur with risk.
B. (Cost + Benefit + Business Risk) / Insurable Risk.
C. how likely the event is to occur with risk.
D. Risk Probability x Amount At Stake.
E. the severity of the consequences.
Answer: D
Q275. All of the following are true regarding Communications Planning except for which one?
A. Communications requirements analysis, communications technology, and PMIS are tools and techniques of this process.
B. It's the only output of the Communications Planning process.
C. It's tightly linked with enterprise environmental factors and organizational influences, and lessons learned and historical information are two inputs that should get a lot of attention during this process.
D. It should be completed as early in the project phases as possible.
Answer: A
Q276. Monitor and control project work is a process of which of the following knowledge areas?
A. Project risk management
B. Project scope management
C. Project time management
D. Project integration management
Answer: D
Q277. You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them with training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following statements is true?
A. This condition is known as culture shock.
B. This is the result of jet lag and travel fatigue.
C. This is the result of working with teams of people from two different countries.
D. This condition is known as globalculturalism.
Answer: A
Q278. Which is an input to the Collect Requirements process?
A. Requirement documentation
B. Organizational process assets
C. Requirements management plan
D. Stakeholder register
Answer: D
Q279. You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525. What is VAC?
A. 25
B. 30
C. 20
D. 70
Answer: A
Q280. You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?
A. Monitoring and Controlling
B. Initiating
C. Executing
D. Planning
Answer: D
Q281. A project team member has been having a big disagreement with another team member for over two months when the other team members become involved. The issues are complex, but you have specific experience in the area and know what needs to be done. The BEST choice would be to:
A. Make the decision yourself.
B. Strive for fair resolution of the issue.
C. Ask the other team members to stay out of the issue.
D. Bring the team together and work out the issue to a win-win solution.
Answer: B
Q282. Which is a true statement regarding project governance?
A. Project governance approach must be described in the project management plan.
B. Project governance is independent of the organization or program sponsoring it.
C. Once a project has begun, it is not necessary to formally initiate each project phase.
D. Review of project performance and key deliverables is not required for each project phase.
Answer: A
Q283. Which of the following equations is used to calculate cost variance?
A. EV-AC
B. AC-EV
C. AC+EV
D. AC/EV
Answer: A
Q284. Which of the following is generally the MOST CORRECT use of a project network diagram?
A. Showing the project schedule
B. Documenting activity interdependencies
C. Defining project resources
D. Defining the project costs
Answer: B
Q285. Which of the following is an example of a tool used in Plan Quality?
A. Fishbone diagram
B. Quality audit
C. Cause and effect diagram
D. Benchmarking
Answer: D