Q31. A person is writing a document identifying the business need for a project and is including a description of the product created by the project. She includes a list of stakeholders and pre assigned resources. What is the role of this person on the project?
A. The project manager for the project or a company functional manager
B. A member of the project management team working at the direction of the project manager
C. The sponsor or the project manager
D. A manager or executive in the organization who is higher in the corporate hierarchy than theproject manager
Answer: C
Q32. Which of the following choices is a contract closure tool or technique?
A. Contract plan
B. Procurement plan
C. Closure process
D. Procurement audits
Answer: D
Q33. Objectives can be described as all of the following except for which one? Choose the least correct answer.
A. The monetary units used to express the cost criteria for the project
B. The functionality and specific conditions that must be met in order to satisfy the project, contract, standard, or specification
C. The quantifiable results used to measure project success that should include schedule, cost, and quality criteria
D. The purpose for undertaking the project
Answer: B
Q34. A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.
A. 1,9
B. 9,1
C. 1,1
D. 9,9
E. 5,5
Answer: A
Q35. The work that must be done in order to deliver a product with the specified features and functions is:
A. Project verification
B. Project scope
C. Project control
D. Product scope
Answer: B

Up to the minute PMP exam fees:
Q36. All the following are needed to create the WBS EXCEPT:
A. Organizational process assets.
B. Quality measurements.
C. Requirements documentation.
D. Project scope statement.
Answer: B
Q37. In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1.
For this data set, it is correct to say that the process:
A. is under control.
B. is out of control.
C. has an increasing trend.
D. has a decreasing trend.
Answer: B
Q38. A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
A. Resource leveling
B. Schedule compression
C. Critical chain
D. Adjusting leads and lags
Answer: B
Q39. You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following statements is true?
A. Performance measurement baselines might be affected by scope changes.
B. Project scope change uses workarounds to correct unexpected problems with scope change.
C. Project scope change uses inspection to determine whether change has occurred.
D. Project scope changes do not require CCB approval.
Answer: A
Q40. Constraints do not include:
A. Expected staff assignments
B. Collective bargaining
C. Organizational structure of the performing organization
D. Impacts of weather
Answer: D