It is more faster and easier to pass the PMP PMP exam by using Vivid PMP Project Management Professional questuins and answers. Immediate access to the Rebirth PMP Exam and find the same core area PMP questions with professionally verified answers, then PASS your exam with a high score now.
Q106. What is the primary benefit of meeting quality requirements?
A. Quality metrics
B. Less rework
C. Quality control measurements
D. Benchmarking
Answer: B
Q107. A weighting system is a tool for which area of procurement?
A. Plan contracting
B. Request seller responses
C. Select sellers
D. Plan purchase and acquisition
Answer: C
Q108. Which of the following is a project constraint?
A. Twenty-five percent staff turnover is expected.
B. The technology to be used is cutting-edge.
C. Project leadership may change due to volatile political environment.
D. The product is needed in 250 days.
Answer: D
Q109. How is scheduled variance calculated using the earned value technique?
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
Answer: C
Q110. Cost management includes processes that are required to maintain financial control of projects.
These processes may include:
A. economic evaluation
B. cost estimating and cost forecasting
C. cost estimating
D. cost forecasting
E. All of the other alternatives apply.
Answer: E
Q111. The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?
A. 0.80
B. 0.89
C. 1.13
D. 1.25
Answer: A
Q112. Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areas of difference?
A. Withdrawing/Avoiding
B. Forcing
C. Collaborating
D. Smoothing/Accommodating
Answer: D
Q113. Mathematical models using linear programming, dynamic, or algorithm models are considered:
A. form of expert judgment
B. project closing method
C. Project selection criteria
D. Project selection methods
Answer: D
Q114. In which of the team development stages are the teams interdependent and work through issues smoothly and effectively?
A. Norming
B. Forming
C. Storming
D. Performing
Answer: D
Q115. On what is project baseline development established?
A. Approved product requirements
B. Estimated project cost and schedule
C. Actual project cost and schedule
D. Revised project cost and schedule
Answer: B
Q116. The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A. Both 1) conceptual, and 2)post project evaluation
B. cut-over
C. conceptual
D. execution
E. post project evaluation
Answer: C
Q117. Communication in both project and non-project-driven organizations should occur in directions.
A. four
B. one
C. two
D. three
E. five
Answer: E
Q118. While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk events. These adjustments are based on your past project experience when unknown risk events occurred and knocked the project off track. What should you do?
A. Include a management reserve in the budget to try to compensate for the unknown risks, and notify management to expect unknown risks to occur.
B. Document the unknown risk items and calculate the expected monetary value based on probability and impact that may result from the occurrence.
C. Determine the unknown risk events and the associated cost, then add the cost to the project budget as reserves.
D. With the stakeholders, determine a percentage of the known risk budget to allocate to a management reserve budget.
Answer: A
Q119. The project charter:
A. Establishes that organizational structure with the project.
B. Expresses upper management commitment to the project.
C. Provides that authority by which the project will be run.
D. Specifies overall objectives and timeframe of the project.
E. All of the other alternatives apply.
Answer: E
Q120. During project executing, a project team member informs the project manager that a work package has not met the quality metric, and that she believes it is not possible to meet it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in?
A. Perform Quality Assurance
B. Project Control
C. Perform Quality Control
D. Plan Quality
Answer: C