Our pass rate is high to 98.9% and the similarity percentage between our PMP study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMP PMP exam in just one try? I am currently studying for the PMP PMP exam. Latest PMP PMP Test exam practice questions and answers, Try PMP PMP Brain Dumps First.

Q151. Most project (and non-project) managers prefer _____ communications.

A.

Answer: D


Q161. You are a new project manager who has never managed a project before. You have been asked to plan a new project. It would be BEST in this situation to rely on _______ during planning to improve your chance of success.

A. Your intuition and training

B. Stakeholder analysis

C. Historical information

D. Configuration management

Answer: C


Q162. Work authorization forms are needed in order to:

A. Authorize line organizations to charge against the project

B. Develop a structured methodology for release of funds

C. Establish an audit trail

D. All of the other alternatives apply

E. 1) Authorize line organizations to charge against the project and 2)Develop a structured methodology for release of funds

Answer: D


Q163. You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. All prerelease of software is handled through the marketing department. A friend of yours is a certified software instructor. They have asked you for a copy of the software prior to the beta release so they can get familiar with it. What is the most appropriate response?

A. Since your friend is certified to teach your company's brand of software, provide them with a copy of the software.

B. Decline the request since you stand to gain from this transaction by receiving free training.

C. Ask them to sign a nondisclosure agreement before releasing a copy of the software.

D. Decline the request because the software is the intellectual property of the company.

Answer: D


Q164. Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

A. Performance organizations

B. Schedule baselines

C. Performance measurements

D. Change requests

Answer: C


Q165. You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers. You performed this project under contract.

You are in the Closing process and know that product verification is for what purpose?

A. To verify that all the work was completed correctly and satisfactorily

B. To evaluate project goals and ensure that the product of the project meets the requirements

C. To verify the goals of the project and ensure that the product of the project is complete

D. To evaluate all the work of the project and compare the results to project scope

Answer: A