Act now and download your PRINCE2-Exams PRINCE2-Foundation test today! Do not waste time for the worthless PRINCE2-Exams PRINCE2-Foundation tutorials. Download Renewal PRINCE2-Exams PRINCE2 Foundation exam exam with real questions and answers and begin to learn PRINCE2-Exams PRINCE2-Foundation with a classic professional.
2021 Sep PRINCE2-Foundation practice test
Q21. - (Topic 2)
Which is a purpose of the Risk theme?
A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization
Answer: B
Q22. - (Topic 1)
Which product documents the information needed to demonstrate continued business justification?
A. Business Case
B. Communication Management Strategy
C. Project Product Description
D. Quality Management Strategy
Answer: A
19. - (Topic 1)
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
A. Benefits
B. Quality
C. Risk
D. Scope
Answer: B
Q23. - (Topic 2)
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
A. define a coding system to provide a unique identifier for the products within
B. summarize the results of the quality activities performed on
C. provide a framework to design, develop and maintain
D. define the project benefits to be achieved by each of
Answer: C
Q24. - (Topic 1)
Which should be funded by a change budget?
A. Increase in agreed scope
B. Initiation stage
C. Change Authority
D. Handover activities
Answer: A
Q25. - (Topic 2)
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Answer: B

Renewal PRINCE2-Foundation vce:
Q26. - (Topic 1)
Which of the following statements about the Project Initiation Documentation are true?
1.
The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2.
The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q27. - (Topic 1)
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
A. Create a separate Project Board to manage the supplier elements of the project
B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
C. Create user and supplier groups
D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Answer: C
Q28. - (Topic 2)
Which statement about the quality review technique is FALSE?
A. It enables a check to be made on a product's fitness for purpose
B. It defines the quality responsibilities of the project team
C. It supports the management of future changes by providing a baseline for a product
D. It is used to gain wider acceptance of a product by involving key interested parties
Answer: B
Q29. - (Topic 1)
What takes place during the Closing a Project process?
A. The post-project benefits reviews are performed
B. Ownership of the project's products is transferred to the customer
C. An End Stage Report is prepared for the final stage
D. The project closure notification is reviewed and approved
Answer: B
Q30. - (Topic 2)
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
A. Enable the Project Board to decide whether or not to authorize the project
B. Justify the continuing viability of the project
C. Enable the Project Board to decide whether or not to authorize project closure
D. Justify the initiation of a project
Answer: B