Free of prince2 foundation sample exam questions and answers pdf free exam materials and discount pack for PRINCE2-Exams certification for IT professionals, Real Success Guaranteed with Updated prince2 foundation course material free pdf dumps vce Materials. 100% PASS PRINCE2 Foundation exam exam Today!
Q18. - (Topic 2)
Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
Answer: A
Q19. - (Topic 1)
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
A. Those with a financial interest in the project
B. Those who will manage the project on a day-to-day basis
C. Those who will specify the desired outputs of the project
D. Those who will create the project's outputs
Answer: B
Q20. - (Topic 1)
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Ensure the technical integrity of a project
D. Develop a project's products
Answer: A
Q21. - (Topic 2)
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
A. Team Plan
B. Stage Plan
C. Benefits Review Plan
D. Project Plan
Answer: B
Q22. - (Topic 1)
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan
Answer: B
Q23. - (Topic 1)
Which is a typical core activity within configuration management?
A. Issue management
B. Quality inspection
C. Identification
D. Preparation
Answer: C
Q24. - (Topic 1)
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
A. Stage Plan
B. Communication Management Strategy
C. Follow-on action recommendations
D. Quality Management Strategy
Answer: B
Q25. - (Topic 2)
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
Answer: D
Q26. - (Topic 1)
Which should be funded from a change budget?
A. The Starting up a Project process
B. A fallback plan
C. An agreed change to the scope of a project
D. A change to a plan, within allocated tolerances, due to poor estimating
Answer: C
Q27. - (Topic 1)
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
A. Change
B. Cross-functional
C. Unique
D. Risk
Answer: B
Q28. - (Topic 1)
What is an off-specification?
A. A new requirement
B. A quality tolerance
C. A type of issue
D. A major risk
Answer: C
Q29. - (Topic 1)
Which is NOT a purpose of a Benefits Review Plan?
A. Define the period over which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in operational use
C. Define the scope, timing and ownership of the benefit reviews required
D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Answer: A
Q30. - (Topic 2)
Which activity takes place within the Managing a Stage Boundary process?
A. Produce Highlight Reports
B. Take corrective action within the limits of a stage's tolerance
C. Produce an Exception Plan
D. Authorize a Stage Plan for the next stage
Answer: C
Q31. - (Topic 2)
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Answer: A
Q32. - (Topic 2)
Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Answer: A
Q33. - (Topic 1)
Which product records any project outcomes perceived as negative by stakeholders?
A. Business Case
B. Project Plan
C. Communication Management Strategy
D. Project Product Description
Answer: A
Q34. - (Topic 2)
Which is a difference between management and technical stages?
A. Management stages require planning and technical stages do not
B. Technical stages can overlap and management stages cannot
C. Management stages deliver products and technical stages do not
D. Technical stages require resources and management stages do not
Answer: B