Exambible offers free demo for book prince2 foundation exam exam. "PRINCE2 Foundation exam", also known as prince2 foundation course material free exam, is a PRINCE2-Exams Certification. This set of posts, Passing the PRINCE2-Exams prince2 foundation exam questions and answers free exam, will help you answer those questions. The prince2 foundation online exam Questions & Answers covers all the knowledge points of the real exam. 100% real PRINCE2-Exams prince2 foundation course exams and revised by experts!

Q18. - (Topic 2) 

Identify the missing word in the following sentence. The risk response type [ ? ] can be 

used to respond to a threat and an opportunity. 

A. Avoid 

B. Reduce 

C. Share 

D. Transfer 

Answer:


Q19. - (Topic 2) 

How should the Team Manager report that tolerances are forecast to be exceeded? A. Create an Exception Report 

B. Create a Highlight Report 

C. Raise an issue 

D. Grant a concession 

Answer:


Q20. - (Topic 2) 

Which document should record the agreed amount of risk budget for a project? 

A. Project Brief 

B. Project Plan 

C. Risk Management Strategy 

D. Risk Register 

Answer:


Q21. - (Topic 1) 

Which is a benefit of using PRINCE2? 

A. Enables the management of projects as well as of 'business as usual' activities 

B. Can be tailored by leaving out elements of the method for some projects 

C. Can be applied to any type of project 

D. Avoids the need to involve corporate or programme management 

Answer:


Q22. - (Topic 1) 

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions? 

A. Project Brief 

B. Project Initiation Documentation 

C. Project mandate 

D. Benefits Review Plan 

Answer:


Q23. - (Topic 2) 

Which is NOT considered when defining risk tolerance? 

A. A Project Board's attitude towards risk taking 

B. The allocated risk budget 

C. An organization's risk appetite 

D. The amount of risk a Project Board considers acceptable 

Answer:


Q24. - (Topic 1) 

Which does the Executive need to ensure is in place before the project is initiated? 

A. All Work Packages are authorized 

B. An understanding of how the project will contribute to corporate objectives 

C. The Project Plan has been approved 

D. The Project Initiation Documentation is complete 

Answer:

38. - (Topic 1) 

What is the collective name for individuals or groups who may be affected by a project? 

A. Customers 

B. Project Support 

C. Stakeholders 

D. Team members 

Answer:


Q25. - (Topic 2) 

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations? 

A. Only corporate or programme management 

B. Only the Project Board 

C. Only the Project Manager 

D. All levels of management 

Answer:


Q26. - (Topic 1) 

When should the Project Board refer to corporate or programme management for a decision? 

A. The stage requires resources 

B. It is forecast that project level tolerance will be exceeded 

C. The Senior Supplier or Senior User needs to be changed 

D. Any request for change needs to be approved 

Answer:


Q27. - (Topic 1) 

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment? 

A. Specify the desired result 

B. Provide the resources and skills to deliver the desired result 

C. Ensure the technical integrity of a project 

D. Develop a project's products 

Answer:


Q28. - (Topic 1) 

Which is a purpose of the Managing Product Delivery process? 

A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package 

B. Provide a controlled link between the Project Manager and the Team Manager(s) 

C. Enable the Project Board to request updates to the current Team Plan 

D. Establish solid foundations for the project 

Answer:


Q29. - (Topic 1) 

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers? 

A. Create a separate Project Board to manage the supplier elements of the project 

B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages. 

C. Create user and supplier groups 

D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board 

Answer:


Q30. - (Topic 1) 

In what process is the authorization to deliver the project's products given? 

A. Starting up a Project 

B. Initiating a Project 

C. Managing a Stage Boundary 

D. Directing a Project 

Answer:


Q31. - (Topic 1) 

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2? 

A. Those with a financial interest in the project 

B. Those who will manage the project on a day-to-day basis 

C. Those who will specify the desired outputs of the project 

D. Those who will create the project's outputs 

Answer:


Q32. - (Topic 2) 

Which is a responsibility of a risk owner? 

A. Identify risks to the project that might occur in their department 

B. Own and authorize the use of the risk budget to fund risk responses 

C. Manage, monitor and control all aspects of an assigned risk 

D. Determine project risk appetite 

Answer:


Q33. - (Topic 2) 

Which is a purpose of the Quality theme? 

A. Establish how the project will ensure that all products created meet their requirements 

B. Establish quality assurance to maintain the quality management system 

C. Identify all the products of the project to ensure the scope has been adequately defined 

D. Determine the communication needs of the organization's quality assurance function 

Answer:


Q34. - (Topic 2) 

Which is a recommended quality review team role? 

A. Project Manager 

B. Assurance 

C. Project Support 

D. Administrator 

Answer: