Want to know Examcollection PRINCE2-Foundation Exam practice test features? Want to lear more about PRINCE2-Exams PRINCE2 Foundation exam certification experience? Study Breathing PRINCE2-Exams PRINCE2-Foundation answers to Renovate PRINCE2-Foundation questions at Examcollection. Gat a success with an absolute guarantee to pass PRINCE2-Exams PRINCE2-Foundation (PRINCE2 Foundation exam) test on your first attempt.

2021 Sep PRINCE2-Foundation exam question

Q71. - (Topic 2) 

Which should be provided by corporate or programme management before the Starting up a Project process commences? 

A. A Project Brief 

B. Sufficient information to identify the prospective Executive 

C. The Project Initiation Documentation 

D. Authority to initiate a project 

Answer: B 


Q72. - (Topic 2) 

Which is a true statement about PRINCE2 event-driven controls? 

A. Event-driven controls take place at predefined periodic intervals 

B. Event-driven controls are produced at the frequency defined in a Work Package 

C. Event-driven controls are used for decision making 

D. Checkpoint Reports are event-driven controls 

Answer: C 


Q73. - (Topic 2) 

Which describes a risk effect? 

A. The uncertainty expressed as a negative or favourable occurrence 

B. The issue which is affecting the project and has resulted in a risk 

C. The impact(s) on the project objectives should the threat or opportunity occur 

D. The change in the status of a risk in response to actions taken to control it 

Answer: C 


Q74. - (Topic 1) 

What process aims to ensure accurate progress information is provided to the Project Manager? 

A. Starting up a Project 

B. Managing a Stage Boundary 

C. Managing Product Delivery 

D. Directing a Project 

Answer: C 

66. - (Topic 1) 

Which is the Issue Register NOT used for? 

A. Capture external events that are impacting a stage 

B. Record information about a deviation in stage tolerance 

C. Capture any threats or opportunities that might have an impact on a stage 

D. Record any problems identified when authorizing a Work Package 

Answer: C 


Q75. - (Topic 1) 

Which is a purpose of the Directing a Project process? 

A. Create and authorize the project mandate 

B. Ensure that work on products allocated to the team is authorized and agreed 

C. Control the day-to-day running of the project 

D. Delegate day-to-day management of the project to the Project Manager 

Answer: D 


PRINCE2-Foundation question

Rebirth PRINCE2-Foundation practice exam:

Q76. - (Topic 2) 

Identify the missing word in the following sentence. The risk response type [ ? ] can be 

used to respond to a threat and an opportunity. 

A. Avoid 

B. Reduce 

C. Share 

D. Transfer 

Answer: C 


Q77. - (Topic 1) 

Which is an objective of the Managing Product Delivery process? 

A. Sign-off completed Work Packages 

B. Ensure the Business Case is kept under review 

C. Report progress to the Project Board 

D. Ensure that work on products is authorized and agreed with the team 

Answer: D 


Q78. - (Topic 2) 

Which is a purpose of the Quality theme? 

A. Establish how the project will ensure that all products created meet their requirements 

B. Establish quality assurance to maintain the quality management system 

C. Identify all the products of the project to ensure the scope has been adequately defined 

D. Determine the communication needs of the organization's quality assurance function 

Answer: A 


Q79. - (Topic 2) 

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities. 

A. change budget 

B. project budget 

C. project's cost tolerance 

D. project's risk tolerance 

Answer: B 


Q80. - (Topic 2) 

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects. 

A. a solution should be designed for 

B. an issue should be created for 

C. the agreed actions should be recorded for 

D. the chair will approve the solution to 

Answer: C