Q151. - (Topic 3)
A project manager is finalizing the WBS when the resource manager provides a list of project team members. Which of the following is the FIRST thing the project manager should do?
A. Obtain outsourcing approval
B. Conduct a kick-off meeting
C. Interview resources for skill sets
D. Assign resources to all tasks
Answer: C
Q152. - (Topic 3)
A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
A. Reviewing holiday and vacation schedule with all team members.
B. Getting the email address of all the employees.
C. Locating each employee on the map in the office.
D. Understanding the international country code of all the team members.
Answer: A
Q153. - (Topic 3)
When a project manager meets with the stakeholders to receive acceptance of all deliverables, the project manager is:
A. writing the charter.
B. closing the project.
C. managing the scope.
D. identifying the resources.
Answer: B
Q154. - (Topic 2)
Given the following activity:
Provide details of errors within the software that occur during verification testing that provide enough evidence that allows the software developers to resolve the errors.
Which of the following components is this known as within the quality management plan?
A. Quality control
B. Quality metrics
C. Quality baseline
D. Quality assurance
Answer: A
Q155. - (Topic 2)
A change has been approved to move the weekly status meetings from Friday to Tuesday. In addition to notating the change decision in the change log, which of the following documents should be updated?
A. Project plan
B. Communication plan
C. Human resource plan
D. Schedule baseline
Answer: B
Q156. - (Topic 2)
A project manager is in the process of developing a charter. The project manager is concerned about communicating with affected business groups. Which of the following needs to be done to ensure all necessary parties are engaged in the effort?
A. Reviewing the work breakdown structure
B. Identifying the stakeholders
C. Developing the project baseline
D. Drafting the change management plan
Answer: B
Topic 3, Exam Set 3
201. - (Topic 3)
A sponsor decides to change hardware vendors right before the project launch, and does not inform the project team. Which of the following should the project manager do FIRST?
A. Crash the schedule
B. Perform impact analysis
C. Schedule a meeting
D. Review the Pareto chart
Answer: B
Q157. - (Topic 3)
A project manager is asked to provide regular status updates to executive management regarding the current project. To effectively manage the distribution of these updates, which of the following should the project manager MOST likely refer to?
A. Lessons learned library
B. Stakeholder register
C. Issue log
D. Meeting agendas
Answer: B
Q158. - (Topic 3)
During which of the following process groups is the project charter developed?
A. Pre-project setup
B. Project execution
C. Project planning
D. Project control
Answer: A
Q159. - (Topic 1)
The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies?
A. Transferring
B. Enhancing
C. Sharing
D. Exploiting
Answer: C
Q160. - (Topic 1)
A project manager will initially baseline a project when:
A. change requests are approved.
B. stakeholders request project initiation.
C. creating a project charter.
D. tasks and estimates have been identified.
Answer: D