Q21. - (Topic 2) 

While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case. Which of the following types of schedule methods will reflect this? 

A. PERT 

B. CPM 

C. CCM 

D. GERT 

Answer:


Q22. - (Topic 1) 

In the planning phase of a project, which of the following activities is performed? 

A. Solicitation 

B. Perform a feasibility study 

C. Appoint a project team 

D. Project Charter 

Answer:


Q23. - (Topic 1) 

After identifying a change needed in the system, which of the following is the NEXT action the stakeholder should perform? 

A. Inform the developer 

B. Inform the resource manager 

C. Inform the project manager 

D. Inform the project sponsor 

Answer:


Q24. - (Topic 3) 

As a part of quality control, a project manager has been monitoring work performance and analyzing information which has indicated variances to the control limits. Which of the following is the NEXT step the project manager should take? 

A. Implement changes to resolve variances 

B. Make the sponsor aware of variances 

C. Meet with the key stakeholders to discuss variances 

D. Generate a change request outlining the variances 

Answer:


Q25. - (Topic 1) 

A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is: 

A. re-direct the development team. 

B. create a change request. 

C. update the issues log. 

D. hold a meeting with the users. 

Answer:


Q26. - (Topic 1) 

The project team is geographically split between two time zones. Which of the following should be performed by the project manager? 

A. Escalate to the project sponsor with a preference to replace the remote members with local members. 

B. Set up meeting times that are not necessarily a perfect fit, but are fair to both locations. 

C. Schedule two separate meetings at the desired local time for the participants. 

D. Convert traditional meetings into email updates and catch up on an exceptions basis. 

Answer:


Q27. - (Topic 3) 

Which of the following project management tools helps identify trends? 

A. Network diagram 

B. Run chart 

C. Histogram 

D. Check sheet 

Answer:


Q28. - (Topic 1) 

Which of the following steps is required to validate a business case? 

A. Feasibility analysis 

B. Assign costs 

C. Schedule milestones 

D. Identify project scope 

Answer:


Q29. - (Topic 3) 

A project manager is drafting the quality management plan for a rapid improvement event during which the manufacturing team will focus on improving the quality of a widget for a high-volume customer. Which of the following criteria would be MOST beneficial to include in the quality management plan? (Select TWO). 

A. Ishikawa diagrams 

B. Work-in-process counts 

C. Documented quality metrics 

D. Risk response strategies 

E. Current control limits 

F. Root-cause analysis 

Answer: C,E 


Q30. - (Topic 1) 

A project charter should allow the approver to easily identify which of the following? 

A. The specific budget needed to complete the project. 

B. How the risk management plan will be mitigated. 

C. The project’s problem statement. 

D. How the resources for the project will be assigned. 

Answer: