Q141. Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs? 

A. Lessons learned 

B. Supporting details 

C. Program management plan updates 

D. Assumptions 

Answer: A 


Q142. You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors? 

A. Proposals 

B. Statement of work 

C. Program management plan 

D. Request for bid documents 

Answer: B 


Q143. Who prepares the statement of work (SOW) for external projects? 

A. Customer 

B. Project management team 

C. Project Manager 

D. Chief Financial Officer (CFO) 

Answer: A 


Q144. Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor? 

A. RFI 

B. RFP 

C. RFQ 

D. IFB 

Answer: A 


Q145. Which of the following is not a template element that is designed to make the project more effective? 

A. Description of the work packages 

B. Required resources and skills 

C. Required actions to complete the project scope 

D. Contract file 

Answer: D 


PgMP free question

Renew PgMP actual exam:

Q146. You are the program manager of the OFEProgram.Youareworking with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers? 

A. Quality assurance 

B. Scope verification 

C. Quality control 

D. Process improvement 

Answer: A 


Q147. Your program will createnewsoftware andinstall new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals? 

A. Program customer 

B. Program director 

C. Program manager 

D. Business analyst 

Answer: C 


Q148. Which of the following individual should respond to the risk with the preplanned risk response? 

A. Key stakeholder 

B. Project manager 

C. Risk owner 

D. Project sponsor 

Answer: C 


Q149. According to Standard for Program Management,Second Edition,how many knowledge areas are involved for program management? 

A. 7 

B. 5 

C. 9 

D. 11 

Answer: C 


Q150. What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated? 

A. Program charter creation 

B. Feasibility study creation 

C. Business case creation 

D. Program scope statement definition 

Answer: B