PgMP will be the testing signal designed for PMI quiz this also qualifications is just about the respected check-ups which honored within the seller "PMI". That PMI PgMP qualifications can be stated when the beginners qualifications and even sole quiz choice for obtaining PMI qualifications. PMI PgMP quiz will be the primary step designed for experienceing this PMI. It may help the particular individuals to be able to examine ale PMI modern technology. PMI PgMP may be known as one of the better starting up specialized qualifications you are able to engage in. And so, having made the decision to learn designed for PMI you are well on the suitable tabs on a prosperous specialized progress.

2021 Sep PgMP actual test

Q161. You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one? 

A. Stakeholder communication information 

B. Schedule variances 

C. Program schedule updates 

D. Change requests 


Answer: B 


Q162. What does RACI stand for? 

A. Responsible, Account, Confirm, Inform 

B. Responsible, Accountable, Consult, Inform 

C. Roles, Accountable, Confirm, Inform 

D. Roles, Action, Consult, Inform 

Answer: B 


Q163. A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario? 

A. Cost, because the program has an estimate to complete of $1,151,429. 

B. Cost, because the program has a cost variance of -7,500 

C. Schedule, because theprogram's planned value is only $700,000. 

D. Schedule, because the program has a schedule performance index of .88. 

Answer: D 


Q164. As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two? 

A. The project management lifecycle and the project lifecycle are the same thing. 

B. The project management lifecycle is comprised of the phases initiating, planning, executing, monitoring and controlling, and closing. The project lifecycle is comprised of phases that are unique to the project work. 

C. The project managementlifecycle is universal to allprojectsand theproject lifecycle is unique to each project. 

D. The projectmanagementlifecycle is uniqueto each projectwhile the project lifecycle is universal to all projects. 

Answer: C 


Q165. You are the program manager for your organization and you're trying to determine if you buy or build a software solution for your organization. If you build the solution it'll cost you $75,000 to create and it'll cost you $12,000 per month to support. If you hire a vendor they can build the solution for $63,000 but their solution will cost you $15,500 per month to support. How many months would you have to use your in-house solution to equate to the cost of the vendor's solution? 

A. Approximately 6 months 

B. You'll never be able to equate to the cost of the vendor's solution. 

C. Approximately 3.5 months 

D. Approximately 10 months 

Answer: C 


PgMP simulations

Update PgMP free practice exam:

Q166. You are the program manager for the HQM Program.Your program hassixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects? 

A. Program governance 

B. Project management assets 

C. Enterprise environmental factors 

D. Organizational process assets 

Answer: D 


Q167. Which of the following is described in the statement given below? 

"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication." 

A. Governance plan 

B. Organizational chart 

C. Program scope statement 

D. Stakeholder register 

Answer: D 


Q168. Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management? 

A. Change request log 

B. Approved change requests 

C. Change requests 

D. Program management plan 

Answer: B 


Q169. You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion? 

A. The project manager 

B. The program customer 

C. The program stakeholders 

D. The project management team 

Answer: B 


Q170. You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie? 

A. A program is a collection of projects that work together to create one deliverable for the organization 

B. A program is a collection of projects managed to gain benefits for the organization; the organization could not realize the benefits of the project if they were managed independently. 

C. A program is a uniform set of goals that are too large to be managed as one independent project so the project is subdivided intomultipleobjectives led by multiple project managers and orchestrated by one program manager. 

D. A program is a large collection of projects lead by a single project manager. 

Answer: B