NEW QUESTION 1
Which of the following is a tool or technique used in the Determine Budget process?
- A. Variance analysis
- B. Three-point estimating
- C. Bottom-up estimating
- D. Historical relationships
Answer: D
NEW QUESTION 2
In a project, total float measures the:
- A. Ability to shuffle schedule activities to lessen the duration of the project.
- B. Amount of time an activity can be extended or delayed without altering the project finish date.
- C. Cost expended to restore order to the project schedule after crashing the schedule.
- D. Estimate of the total resources needed for the project after performing a forward pas
Answer: B
NEW QUESTION 3
Which of the following is a tool or technique used in the Acquire Project Team process?
- A. Networking
- B. Training
- C. Negotiation
- D. Issue log
Answer: C
NEW QUESTION 4
A method to manage stakeholder expectations in the scope statement is to clearly:
- A. state the guiding principles of the organization.
- B. identify alternatives to generate different approaches.
- C. state what is out of scope.
- D. outline the results of the Delphi techniqu
Answer: C
NEW QUESTION 5
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
- A. Perform Quality Control
- B. Quality Metrics
- C. Perform Quality Assurance
- D. Plan Quality
Answer: C
NEW QUESTION 6
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
- A. Urgent information need
- B. Sensitivity of information
- C. Project environment
- D. Ease of use
Answer: C
NEW QUESTION 7
Which of the following is an input to Direct and Manage Project Execution?
- A. Performance reports
- B. Project charter
- C. Outputs from planning processes
- D. Enterprise environmental factors
Answer: D
NEW QUESTION 8
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
- A. Plan Stakeholder Management
- B. Identify Stakeholders
- C. Manage Stakeholder Engagement
- D. Control Stakeholder Engagement
Answer: A
NEW QUESTION 9
Which is an example of Administer Procurements?
- A. Negotiating the contract
- B. Authorizing contractor work
- C. Developing the statement of work
- D. Establishing evaluation criteria
Answer: B
NEW QUESTION 10
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
- A. Organizational standard processes
- B. Marketplace conditions
- C. Historical information
- D. Templates
Answer: B
NEW QUESTION 11
Which type of chart is a graphic representation of a process showing the relationships among process steps?
- A. Control
- B. Bar
- C. Flow
- D. Pareto
Answer: C
NEW QUESTION 12
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
- A. Plan Procurement Management
- B. Control Procurements
- C. Collect Requirements
- D. Plan Cost Management
Answer: A
NEW QUESTION 13
Which of the following processes are part of the Project Integration Management Knowledge Area?
- A. Develop Project Management Plan, Collect Requirements, Create WBS
- B. Develop Project Management Plan, Control Scope, Develop Schedule
- C. Develop Project Charter, Define Scope, Estimate Costs
- D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase
Answer: D
NEW QUESTION 14
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
- A. Customers.
- B. Business partners.
- C. Sellers.
- D. Functional manager
Answer: B
NEW QUESTION 15
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
- A. Uniform
- B. Continuous
- C. Discrete
- D. Linear
Answer: C
NEW QUESTION 16
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
- A. 1
- B. 0.4
- C. 0.5
- D. 0.8
Answer: D
NEW QUESTION 17
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
- A. Initiating
- B. Monitoring and Controlling
- C. Planning
- D. Closing
Answer: C
NEW QUESTION 18
What provides information regarding the ways people, teams, and organizational units behave?
- A. Organizational chart
- B. Organizational theory
- C. Organizational structure
- D. Organizational behavior
Answer: B
NEW QUESTION 19
Which of the following statements correctly characterizes pull communication?
- A. It includes letters, memos, reports, emails, and faxes.
- B. It requires recipients to access communication content at their own discretion.
- C. It is the most efficient way to ensure a common understanding among all participants.
- D. It is primarily used when the volume of information to be transferred is minima
Answer: B
NEW QUESTION 20
Which tool or technique is required in order to determine the project budget?
- A. Cost of quality
- B. Historical relationships
- C. Project management software
- D. Forecasting
Answer: B
NEW QUESTION 21
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
- A. Quality assurance.
- B. A stakeholder management plan.
- C. Project team building.
- D. Integrated change contro
Answer: D
NEW QUESTION 22
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
- A. Continuous
- B. Discrete
- C. Regulated
- D. Arbitrary
Answer: A
NEW QUESTION 23
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
- A. Limited
- B. Low to moderate
- C. Moderate to high
- D. High to almost total
Answer: C
NEW QUESTION 24
Which organizational process assets update is performed during the Close Procurements process?
- A. Procurement audit
- B. Lessons learned
- C. Performance reporting
- D. Payment requests
Answer: B
NEW QUESTION 25
......