Cause all that matters here is passing the PMI CAPM exam. Cause all that you need is a high score of CAPM Certified Associate in Project Management (PMI-100) exam. The only one thing you need to do is downloading Pass4sure CAPM exam study guides now. We will not let you down with our money-back guarantee.
Free CAPM Demo Online For PMI Certifitcation:
NEW QUESTION 1
A project has an EV workdays, an AC workdays, and a PV workdays. What should be the concern?
- A. There is a cost underrun.
- B. There is a cost overrun.
- C. The project may not meet the deadline.
- D. The project is 20 days behind schedul
Answer: B
NEW QUESTION 2
A tool or technique in Perform Quality Control that a project manager would use is:
- A. quality audits.
- B. process analysis.
- C. benchmarking.
- D. inspection.
Answer: D
NEW QUESTION 3
Which output is the approved version of the time-phased project budget?
- A. Resource calendar
- B. Scope baseline
- C. Trend analysis
- D. Cost baseline
Answer: D
NEW QUESTION 4
Which of the following is an output of the Monitor and Control Project Work process?
- A. Change requests
- B. Performance reports
- C. Organizational process assets
- D. Project management plan
Answer: A
NEW QUESTION 5
Those who enter into a contractual agreement to provide services necessary for a project are:
- A. buyers
- B. sellers
- C. business partners
- D. product users
Answer: B
NEW QUESTION 6
A disadvantage associated with virtual teams is that they:
- A. Require communication technology that is not readily available.
- B. Create difficulties when including people with disabilities.
- C. Often cannot accommodate teams that work different hours or shifts.
- D. Create the possibility for misunderstandings to aris
Answer: D
NEW QUESTION 7
An input to the Plan Stakeholder Management process is:
- A. The project charter.
- B. The stakeholder analysis.
- C. A communication management plan.
- D. A stakeholder registe
Answer: D
NEW QUESTION 8
Tools and techniques used in Direct and Manage Project Work include:
- A. Process analysis and expert judgment
- B. Analytical techniques and a project management information system
- C. Performance reviews and meetings
- D. Expert judgment and meetings
Answer: D
NEW QUESTION 9
An intentional activity to modify a nonconforming product or product component is called:
- A. defect repair
- B. work repair
- C. corrective action
- D. preventive action
Answer: A
NEW QUESTION 10
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
- A. 0.45
- B. 0.56
- C. 0.70
- D. 1.36
Answer: C
NEW QUESTION 11
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
- A. Product scope description
- B. Procurement statement of work
- C. Project schedule
- D. Work breakdown structure (WBS)
Answer: B
NEW QUESTION 12
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
- A. Control chart
- B. Flowchart
- C. Run chart
- D. Pareto chart
Answer: B
NEW QUESTION 13
Work performance information and cost forecasts are outputs of which Project Cost Management process?
- A. Estimate Costs
- B. Plan Cost Management
- C. Determine Budget
- D. Control Costs
Answer: D
NEW QUESTION 14
Which is an input to the Verify Scope process?
- A. Performance report
- B. Work breakdown structure (WBS)
- C. Requested changes
- D. Project management plan
Answer: D
NEW QUESTION 15
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
- A. Estimate Costs
- B. Control Costs
- C. Determine Budget
- D. Plan Cost Management
Answer: B
NEW QUESTION 16
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
- A. Cost variance (CV)
- B. Cost performance index (CPI)
- C. Budget at completion (BAC)
- D. Variance at completion (VAC)
Answer: B
NEW QUESTION 17
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
- A. Cause and effect diagram
- B. Control charts
- C. Pareto chart
- D. Histogram
Answer: B
NEW QUESTION 18
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific
sequence is desired, even though there may be other acceptable sequences?
- A. External
- B. Internal
- C. Mandatory
- D. Discretionary
Answer: D
NEW QUESTION 19
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
- A. Define Activities
- B. Direct and Manage Project Work
- C. Develop Project Management Plan
- D. Develop Project Charter
Answer: D
NEW QUESTION 20
An output of the Create WBS process is:
- A. Scope baseline.
- B. Project scope statement.
- C. Organizational process assets.
- D. Requirements traceability matri
Answer: A
NEW QUESTION 21
Whose approval may be required for change requests after change control board (CCB) approval?
- A. Functional managers
- B. Business partners
- C. Customers or sponsors
- D. Subject matter experts
Answer: C
NEW QUESTION 22
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
- A. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
- B. Cost-Reimbursable Contract (CR)
- C. Firm-Fixed -Price Contract (FFP)
- D. Fixed-Price-Incentive-Fee Contract (FPIF)
Answer: C
NEW QUESTION 23
The procurement process that documents agreements and related documentation for future reference is known as:
- A. Plan Procurements.
- B. Control Procurements.
- C. Close Procurements.
- D. Conduct Procurement
Answer: C
NEW QUESTION 24
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
- A. smooth/accommodate.
- B. force/direct,
- C. collaborate/problem solve,
- D. compromise/reconcil
Answer: C
NEW QUESTION 25
......