Cause all that matters here is passing the CompTIA PK0-003 exam. Cause all that you need is a high score of PK0-003 CompTIA Project+ (2009) exam. The only one thing you need to do is downloading Testking PK0-003 exam study guides now. We will not let you down with our money-back guarantee.
Q1. - (Topic 3)
A project manager is holding a workshop to identify objectives, review legal and regulatory requirements, and establish and maintain performance measures. Which of the following is being performed?
A. Quality control
B. Quality objectives
C. Quality assurance
D. Quality audit
Answer: C
Q2. - (Topic 2)
Which of the following tools should be used to analyze quality issues? (Select TWO).
A. Risk register
B. Pareto chart
C. Histogram
D. SWOT analysis
E. RACI chart
Answer: B,C
Q3. - (Topic 1)
The stakeholder has notified the project manager that new priorities have caused them to shift all of the business subject matter expert resources to a new project for one year. The BEST course of action for the project manager is:
A. phase gate review.
B. project cancellation.
C. project completion.
D. stage completion.
Answer: B
Q4. - (Topic 3)
The project manager informs the team that the client has approved a change in the direction of the project. Which of the following tasks should the project manager perform NEXT?
A. Update cost and schedule baselines
B. Schedule meetings based on the project schedule
C. Review the communications plan and follow the steps
D. Establish project quality by using the quality management metrics
Answer: A
Q5. - (Topic 1)
A project manager has been presented a set of documents containing why a project is needed, how it fits in with the company objectives, and the revenue that will be generated by the product. Which of the following has the project manager just received?
A. A business case
B. A charter
C. Key project deliverables
D. Project objectives
Answer: A
Q6. - (Topic 2)
Which of the following items would be found in a project scope statement?
A. Key performance indicators
B. High-level cost estimates
C. Acceptance criteria
D. Bottom-up estimates
Answer: A
Q7. - (Topic 2)
A project manager is meeting with the key stakeholders to understand the problem, gather business requirements, and identify project objectives. Which of the following allows this information to be formally documented and allows the project manager to measure success?
A. Project management plan
B. Project charter
C. Request for proposal
D. Statement of work
Answer: B
Q8. - (Topic 2)
A project manager identifies that product components being built are consistently failing to meet well-defined metrics. Which of the following is the appropriate action?
A. Perform change management
B. Initiate communication
C. Increase quality control
D. Manage project budget
Answer: A
Q9. - (Topic 2)
A project manager has projected an overwhelming response to a product launch. Which of the following BEST describes this event?
A. A constraint
B. A risk
C. A performance index
D. An issue
Answer: B
Q10. - (Topic 3)
Which of the following is a part of the scope baseline that contains details of the work detail, inputs, outputs, roles and responsibilities, duration, and required resources?
A. WBS dictionary
B. RACI chart
C. Work package
D. Scope statement
Answer: A